Project Updates
FOR SITE TRIPPING: Call or Text:(0926)5570824 Look for: Maria Theresa
OCTOBER 2007
- Banyan Ridge
- Mandala West
- Mandala North
- Mandala South
Upcoming Project: Mandala 2 Activity: Road Tracing Ongoing Projects: - The Ranch
-Gate and Guard House -Land Development - Mandala East
-Land Development - Spine Road
-Phase 2A - 1st 2 Lane -Concreting of 3rd Lane ------ The Ranch Gate and Guardhouse ------ Accomplishment 95.68% The Ranch Land Development Accomplishment 97% (As of October 8, 2007) | Drainage System | 90% | | Water System | 98% | | Road Concreting | 100% | | Sodding Works | 70% | *Sodding and Block Preparation *Rectification Works ------ CONSTRUCTION OF HOUSE MODELS AT THE RANCH ------ | HOUSE MODEL | ACCOMPLISHMENT | | Upland | 71% | | Ridge Deck | 69.46% | | Hartford | 77% | UPLAND HOUSE MODEL (Blk 3 Lot 6) *CHB Laying *Installation of roof framing for Upland RIDGEDECK HOUSE MODEL (Blk3 Lot 3) *CHB Laying *Construction of entrance stairs of Ridgedeck *Construction of CHB wall partitions at 2nd floor of Ridgedeck HARTFORD HOUSE MODEL (Blk1 Lot 5) *Wall plastering and installation of concrete mouldings *Stairs at Hartford
----- Mandala East Land Development ----- Accomplishment 97% (As of October 8, 2007) | Drainage System | 100% | | Water System | 81.29% | | Road Construction | 100% | | Masonry Barrier | 100% | Road 17: Concreted Road 14 Concreting ----- Spine Road ----- Accomplishment (As of October 8, 2007) - PHASE 2A 97.54%
Drainage System 92.37% Road Works 100% - 3RD LANE 73%
Road Works 82% 1st & 2nd Stage Road Concreting at The Ranch Entrance 1st Stage Road Concreting at Mandala Phase 2 Entrance Base Course Preparation and Formworks for Curb & Gutter: Center Island
|